WARS



Week of May 7th
Task Team Status Estimated Actual Comments
Documents

All

Finished 2 2 Complete documents.
Create DVD

All

Finished 1 1 Burn the DVD to give to the clients.


Week of April 30th
Task Team Status Estimated Actual Comments
Program

All

Finished 2 2 Finishing touches
Final Presentation

All

Finished 5 5 Practice and do the presentation.
Documents All In Progess 5 5 Finalize all documents.


Week of April 24th
Task Team Status Estimated Actual Comments
Program

All

In Progress   Polishing & debugging
Final Presentation

All

In Progress 3   Getting ready for the final presentation.
Documents All In Progess 10   User and developer manuals as well as updating old docs.

 

Week of April 18th
Task Team Status Estimated Actual Comments
Program

Witter,
Scott,
Walton

In Progress 10 9 Polishing & debugging
SRS

All

Finished 2   Getting ready for the SRS on Friday.
Documents All In Progess 12   User and developer manuals as well as updating old docs.

 

Week of April 4-11th
Task Team Status Estimated Actual Comments
Program

Witter,
Scott,
Walton

In Progress 20 20 Polishing & debugging
SRS

All

Finished 20 20 Continue working on SRS poster
Documents All In Progess 6 6 User and developer manuals as well as updating old docs.
North Texas Presentation All Finished 6 6 Rehearsed and presented

 

Week of March 26th
Task Team Status Estimated Actual Comments
Program

Witter,
Scott,
Walton

In Progress 6 6 Polishing
SRS Poster

Kyle

In Progress 2 2 Continue working on SRS poster
Database Witter,
Davis
Finished 3 3 Getting the datadirectory to work and adding more test data.
North Texas Presentation All Finished 2 2 Make powerpoint and reherse it.

 

Week of March 26th
Task Team Status Estimated Actual Comments
Program

Witter,
Scott,
Walton

In Progress 6 6 Continue working on the knee flex angle.
SRS Poster

Kyle

In Progress 4 4 Continue working on SRS poster
Database Witter,
Davis
In progress 5 5 Adding more fields to the patient table represent hip measurements.
Documentation Walton In Progress 1 1 Updated documentation and architecture.

 

Week of March 19th
Task Team Status Estimated Actual Comments
Program

Witter,
Scott,
Walton

In Progress 6 6 Fixing the knee flex angle.
SRS Poster

All

In Progress 4 4 Continue working on SRS poster
Database Witter,
Davis
In progress 8 8 More injury functionality as well as starting to add test data and components in to the database.

 

Week of March 5th
Task Team Status Estimated Actual Comments
Program

Witter,
Scott

Finished 6 6 Working to integrate database code into the existing program.
SRS Poster

All

In Progress 4 4 Continue working on SRS poster

 

Week of February 26th
Task Team Status Estimated Actual Comments
Database

Witter,
Davis

In Progress 6 16 Start figuring out how to store test data.
Iteration 3

Scott,
Walton,

In Progress 7 6 Tweaking the program to be object oriented. Testing.
Test Manual Kyle In Progress 4 0 Working on test manual.
SRS Poster All In Progress 4 4 Create poster rough draft.

 

Week of February 19th
Task Team Status Estimated Actual Comments
Database

Witter,
Davis,
Walton

Finished 6 20 Finish up add patient functionality and GUI.
Iteration 3

Scott,
Walton,
Kyle

In Progress 7 6 Tweaking the program to be object oriented. Testing.

 

Week of February 12th
Task Team Status Estimated Actual Comments
Database

Witter,
Davis

In Progress 6 6 Finish up add patient functionality and GUI.
Iteration 3

Scott,
Walton,
Kyle

In Progress 8 6 Foward/Backward Jogging
Website Davis Finished 1 2 Maintenance

 

Week of February 5th
Task Team Status Estimated Actual Comments
Database

Witter,
Davis

In Progress 6 6 Working on insert, search, and update patient functionality.
Programming

Scott,
Walton,
Kyle

In Progress 8 8 Fixing Lateral Bounding, getting Foward Jogging and Backward Jogging to work.
SRS Abstract

Scott,
Walton,
Kyle

Finished 2 3 Wrote the abstract for the SRS

 

Week of January 29th
Task Team Status Estimated Actual Comments
Database

Witter,
Davis

In Progress 6   Working on getting patient data in to the database
Iteration 2 Scott,
Walton,
In Progress 8   Lateral bounding functionality
Faculty Presentation Kyle In Progress 2 2 Making presetation Power Point

 

Week of January 22nd
Task Team Status Estimated Actual Comments
Database

Witter,
Davis

In Progress 8 6 Working on getting patient data in to the database
Iteration 2 Scott,
Walton,
In Progress 10 9 Lateral bounding functionality
Documentation Kyle Finished 4 4 Updating

 

Week of January 14th
Task Team Status Estimated Actual Comments
Database Witter, Davis In Progress 10 8 Visual Studio database
Iteration 2

Scott,
Walton,
Kyle

In Progress 16 10 Adding functionality for first 2 components

 

Week of January 1st
Task Team Status Estimated Actual Comments
Database Witter In Progress 3 3 Visual Studio database
Iteration 2

Scott,
Walton

In Progress 16 16 Adding functionality for first 2 components

 

Week of December 17th
Task Team Status Estimated Actual Comments
Test Plan Kyle In Progress 2 2 Working on elements for test planning
Iteration 2 Scott, Walton In Progress 16 20 Adding functionality for first 2 components

 

Week of December 12th
Task Team Status Estimated Actual Comments
All Documents and Presentation All Complete 3 4 Finished documents and practiced presentation
Iteration 1 coding All In Progress 5 5 coding
Website Davis Complete 1 1 Update

 

Week of December 4th
Task Team Status Estimated Actual Comments
All Document and Presentation All In Progress 4 14 Edited Design document and made the final presentation
Database Davis, Witter In Progress 4 7 Create diagrams and SQL database
Iteration 1 coding Scott, Chris In Progress 4 14 coding
Website Davis Complete 3 3 Update


Week of November 29th
Task Team Status Estimated Actual Comments
Requirement Revision Walton, Kyle, Witter Pending Approval 3 3 Edited Requirements document
Project Plan Revision Walton, Witter Pending Approval 1 1 Edited Project Plan
Design Document (GUI) Scott In Progress 3 3 Screenshots and descriptions
Website Davis, Scott In Progress 3 2 Update



Week of November 20th
Task Team Status Estimated Actual Comments
Database Design Davis, Witter In Progress 4 4 Start on the database design
Sequence Diagrams Kyle, Scott, Walton In Progress 3 0 Create sequence diagrams
GUI Scott Complete 3 3 Updating GUI
Class Diagrams Kyle, Scott, Witter, Walton In Progress 4 0 Create class diagrams

 

Week of November 13th
Task Team Status Estimated Actual Comments
Design Document All In Progress 4 4 Start on the design document
Website Davis In Progress 2 2 Update website
GUI Scott Complete 3 3 Updating GUI
Use Cases All Complete 3 3 Added and edited Use Cases
Kinect programming Walton, Scott In Progress 5 6 Got the kinect to recognize joints

 


Week of November 6th
Task Team Status Estimated Actual Comments
Software Requirements All In Progress 5 5 Finishing up and revising the requirements
Website Davis In Progress 4 4 Finish the website and WARs
Presentation All Complete 1 2 Chris Walton's presentation for the Industry Meeting
GUI Scott In Progress 2 2 Updating GUI





Week of October 28th
Task Team Status Estimated Actual Comments
Software Requirements All In Progress 4 4 Finished everything except for Use Cases
GUI Prototype Scott Complete 4 4 Finished both GUI prototypes in time for the client meeting
Client Meeting All Complete 1 1 Chris Walton missed due to illness
Website Davis In Progress 2 2 Still working on the 'non home-page' pages

 