Team BullFROG Schedule

A list of items Team BullFROG will be completing and have completed.

Task Duration Start Finish
Project Proposal
4 Days
2012-09-29
2012-10-02
Project Plan
3 Days
2012-10-02
2012-10-04
Project Support Environment Setup
8 Days
2012-10-04
2012-10-11
Software Requirements Specification
8 Days
2012-10-11
2012-10-18
Design Document
24 Days
2012-10-23
2012-11-15
Iteration 1
28 Days
2012-11-15
2012-12-13
Iteration 2
46 Days
2012-12-13
2013-01-25
Iteration 3
26 Days
2013-01-25
2013-02-20
Test Plan
34 Days
2013-01-25
2013-02-28
NTSAC Abstract
30 Days
2013-02-14
2013-03-14
Iteration 4
30 Days
2013-02-15
2013-03-15
SRS Abstract
45 Days
2013-02-12
2013-03-29
NTSAC Presentation
3 Days
2013-03-29
2013-03-31
User Manual
7 Days
2013-04-01
2013-04-07
Developer Manual
10 Days
2013-04-01
2013-04-10
SRS Poster
12 Days
2013-04-01
2013-04-12
SRS Presentation
1 Day
2013-04-19
2013-04-19
Final DVD Submission
1 Days
2013-04-23
2013-04-23
Final Presentation
1 Days
2013-05-02
2013-05-02